Components:
FOOTINGs
- 5 under bearing walls 16 under exterior walls
FOUNDATION
- 8โ€x8โ€x32โ€ pressure treated rectangular columns (21 total) that rest on top of the footings
- Anchors are spaced 4โ€™ apart in each load-bearing wall (all exterior walls and both interior walls)
CONCRETE DRIVEWAY
- 6โ€ concrete to support 4500psi with a slight slope for water runoff.
FLOORING
I. Main Floor
A. The concrete foundation acts as the flooring in order to support heavy machinery and vehicles.
B. 50ft by 35ft; 6โ€ thick to support 4500psi
II. Loft
A. Twenty-two 2โ€x12โ€ southern yellow pine lumber, 15โ€ on-center spacing, for floor joists
B. 35ft by 30ft
C. Built for 40psf
WALLS (excluding doors)
General info:
- each corner (4) has 3 studs and there are 4 T-junctions that contain 4 studs each
- Each wall had a double top plate made of 2โ€x8โ€ southern pine lumber.
- Each wall has 15โ€ on-center spacing
- SIDING: one layer of plywood sheathing with another layer of steel siding. Both are nailing into place
I. North Wall
II. East Wall
III. South Wall
IV. West Wall
V. Load Bearing Wall 1
VI. Load Bearing Wall 2
DOORS
I. Regular Doors
A. Headers are made of three 2โ€x8โ€x4โ€™ southern pine planks nailed together with (cut in half)
1/2โ€x4โ€x8โ€™ plywood fillers in between each plank (2 fillers)
B. Has 2 king studs, 2 cripple studs, and 2 jack studs (all from 2โ€x8โ€ lumber)
II. Garage Door
A. Headers are made with three 2โ€x8โ€x16โ€™ southern pine planks nailed together with 1/2โ€x4โ€x8โ€™
plywood fillers in between each plank (2 fillers)
B. Has 2 king studs, 24 cripple studs, and 2 jack studs (all from 2โ€x8โ€ lumber)
III. Barn-Style Doors
A. Headers are made with three 2โ€x8โ€x8โ€™ southern pine planks nailed together with two 1/2โ€x4โ€x8โ€™
plywood fillers in between each plank (2 fillers)
B. Has 2 king studs, 4 cripple studs, and 2 jack studs (all from 2โ€x8โ€ lumber)
pf3

Partial preview of the text

Download Construction Project Proposal and more Study notes Construction in PDF only on Docsity!

Components:

FOOTINGs

  • 5 under bearing walls 16 under exterior walls FOUNDATION
  • 8โ€x8โ€x32โ€ pressure treated rectangular columns (21 total) that rest on top of the footings
  • Anchors are spaced 4โ€™ apart in each load-bearing wall (all exterior walls and both interior walls) CONCRETE DRIVEWAY
  • 6โ€ concrete to support 4500psi with a slight slope for water runoff. FLOORING I. Main Floor A. The concrete foundation acts as the flooring in order to support heavy machinery and vehicles. B. 50ft by 35ft; 6โ€ thick to support 4500psi II. Loft A. Twenty-two 2โ€x12โ€ southern yellow pine lumber, 15โ€ on-center spacing, for floor joists B. 35ft by 30ft C. Built for 40psf WALLS (excluding doors) General info:
  • each corner (4) has 3 studs and there are 4 T-junctions that contain 4 studs each
  • Each wall had a double top plate made of 2โ€x8โ€ southern pine lumber.
  • Each wall has 15โ€ on-center spacing
  • SIDING: one layer of plywood sheathing with another layer of steel siding. Both are nailing into place I. North Wall II. East Wall III. South Wall IV. West Wall V. Load Bearing Wall 1 VI. Load Bearing Wall 2 DOORS I. Regular Doors A. Headers are made of three 2โ€x8โ€x4โ€™ southern pine planks nailed together with (cut in half) 1/2โ€x4โ€x8โ€™ plywood fillers in between each plank (2 fillers) B. Has 2 king studs, 2 cripple studs, and 2 jack studs (all from 2โ€x8โ€ lumber) II. Garage Door A. Headers are made with three 2โ€x8โ€x16โ€™ southern pine planks nailed together with 1/2โ€x4โ€x8โ€™ plywood fillers in between each plank (2 fillers) B. Has 2 king studs, 24 cripple studs, and 2 jack studs (all from 2โ€x8โ€ lumber) III. Barn-Style Doors A. Headers are made with three 2โ€x8โ€x8โ€™ southern pine planks nailed together with two 1/2โ€x4โ€x8โ€™ plywood fillers in between each plank (2 fillers) B. Has 2 king studs, 4 cripple studs, and 2 jack studs (all from 2โ€x8โ€ lumber)

CEILING

I. Consists of twenty-five 2โ€x8โ€ lumber, 2โ€™ on-center spacing ROOFING I. Truss A. Gable roof truss B. 2 king studs, fifty-two studs with 2โ€™ on-center spacing (all 2โ€x8โ€ lumber) II. Supporting beams A. Eighteen 15โ€™ support studs using 2โ€x8โ€ lumber with ~2โ€™ on-center spacing III. Outer framing A. Eighteen 30โ€™ studs using 2โ€x8โ€ lumber with ~2โ€™ on-center spacing B. Has very, very slight overhang IV. Outer materials A. Plywood sheathing over the rafters then wood steel shingles over that. Both are nailed into place.

Materials + Cost Calculations

Material Specification Amount (and units) Price Per Unit Total Concrete Blocks 689 blocks $1.60/block $1,102. Brick & Mortar 65 bags $5.70/bag $370. Slabs 91.19 cu.yd $130/cu.yd $11,854. Rebar #4 20โ€™ rebar 109.83 ft $12.52/20ft of rebar $68. Gravel (pea fill) 21.6 cu.yd $30/cu.yd $648. Wire Mesh #5 wire mesh 2750 sq.ft ~ 4 rolls $150/roll $ Anchor Bolts 48 anchors $2.50/bolt $ Wood Plywood Filler (ยฝโ€x4โ€x8โ€™) 8 planks $21/unit $ (sheathing)---> Plywood Boards (4โ€™x8โ€™) 218 boards $32.28/board $7,037. 2โ€x8โ€ Southern Pine 210 planks $51/plank $10, 2โ€x12โ€ Southern Pine 30 planks $73.79/plank $2,213. Sill Plate Gasket ยผโ€x 7.5โ€x50โ€™ rolls 201 ft ~ 4 rolls $11/roll $ Framing Nails 130 nails/lb 1 box $124.50/50lb box $124. Cap Nails 1lb box 4 boxes $6/boxes $