STANDARD EQUIPMENT CAPABILITY ESTIMATES
ITEM NO.
TYPE OF WORK EQUIPMENT USED
CAPABILITY ADOPTED
100 Clearing and Grubbing Bulldozer 3200 - 4000 sq.m./day
102 Excavation Bulldozer 200 cu.m./day
Compaction Road Roller 240 - 320 cu.m./day
104 Embankment Payloader 240 - 320 cu.m./day
Compaction Road Roller 240 - 320 cu.m./day
Quarrying Bulldozer 400 cu.m./day
105 Sub-grade Preparation Grader 2400 sq.m./day
Compaction Road Roller 240 - 320 cu.m./day
200 Aggregate Sub-Base Course
Grader 2400 sq.m./day
Road Roller 240 - 320 cu.m./day
Water Truck 8000 sq.m./day
STANDARD MANUAL CAPABILITY ESTIMATES
ITEM NO.
TYPE OF WORK MANPOWER REQT.
CAPABILITY ADOPTED
100 Canal Excavation 3.00 cu.m./day
Backfilling 2.00 cu.m./MD
103 Structure Excavation 1.5 cu.m./MD
200 Agg. Sub-Base Course
Spreading 2.50 cu.m./MD
500 RC Pipe Culverts
12" Crew Foreman 16 pcs/day
18 Mason 14 pcs/day
24 Carpenter/Steelman 12 pcs/day
30 12 Laborers 10 pcs/day
36 1 bagger mixer 8 pcs/day
10 mins/bag
504 Grouted Riprap Crew Foreman 7.50 cu.m./day
2 - mason
10 - Laborers
1 bagger mixer
5 Stone Masonry
Laying of Materials Boulders 1.50 cu.m./day
Concreting Crew Foreman 6.00 cu.m./day
2 - Mason
10 - Laboreres
1 bagger mixer
pf3
pf4
pf5
pf8
pf9
pfa
pfd
pfe
pff
pf12
pf13
pf14
pf15
pf16

Partial preview of the text

Download STANDARD EQUIPMENT CAPABILITY ESTIMATES and more Summaries Mathematics in PDF only on Docsity!

STANDARD EQUIPMENT CAPABILITY ESTIMATES

ITEM NO. TYPE OF WORK EQUIPMENT USED CAPABILITY ADOPTED 100 Clearing and Grubbing Bulldozer 3200 - 4000 sq.m./day

102 Excavation Bulldozer 200 cu.m./day Compaction Road Roller 240 - 320 cu.m./day

104 Embankment Payloader 240 - 320 cu.m./day Compaction Road Roller 240 - 320 cu.m./day Quarrying Bulldozer 400 cu.m./day

105 Sub-grade Preparation Grader 2400 sq.m./day Compaction Road Roller 240 - 320 cu.m./day

200 Aggregate Sub-Base Course Grader 2400 sq.m./day Road Roller 240 - 320 cu.m./day Water Truck 8000 sq.m./day

STANDARD MANUAL CAPABILITY ESTIMATES

ITEM NO. TYPE OF WORK MANPOWER REQT. CAPABILITY ADOPTED

100 Canal Excavation 3.00 cu.m./day Backfilling 2.00 cu.m./MD

103 Structure Excavation 1.5 cu.m./MD

200 Agg. Sub-Base Course Spreading 2.50 cu.m./MD

500 RC Pipe Culverts 12" Crew Foreman 16 pcs/day 18 Mason 14 pcs/day 24 Carpenter/Steelman 12 pcs/day 30 12 Laborers 10 pcs/day 36 1 bagger mixer 8 pcs/day 10 mins/bag

504 Grouted Riprap Crew Foreman 7.50 cu.m./day 2 - mason 10 - Laborers 1 bagger mixer

5 Stone Masonry Laying of Materials Boulders 1.50 cu.m./day Concreting Crew Foreman 6.00 cu.m./day 2 - Mason 10 - Laboreres 1 bagger mixer

STANDARD SPECIFICATIONS FOR HIGHWAYS, BRIDGES AND AIRPORTS

PART I EARTHWORKS:

Item 100 - Clearing and Grubbing Item 101 - Removal of Structures and Construction Item 102 - Excavation Item 103 - Structure Excavation Item 104 - Embankment Item 105 - Sub-grade Preparation Item 106 - Compaction Equipment and Density Control Strips Item 107 - Overhaul

PART II SUB-BASE & BASE COURSE:

Item 200 - Aggregate Sub-base Course Item 201 - Aggregate Base Course Item 202 - Crushed Aggregate Base Course Item 203 - Portland Cement Stabilized Road Mix Base Course Item 204 - Asphalt Stabilized Road Mix Base Item 205 - Portland Cement Treated Plant Mix Base Course Item 206 - Aggregate Stockpile

PART III SURFACE COURSE:

Item 300 - Aggregate Surface Course Item 301 - Bituminous Prime Coat Item 302 - Bituminous Tack Coat Item 303 - Bituminous Seal Coat Item 304 - Bituminous Surface Treatment Item 305 - Bituminous Penetration Macadam Pavement Item 306 - Bituminous Road Mix Surface Item 307 - Bituminous Plant Mix Surface Course-General Item 308 - Bituminous Plant Mix Surface Course-Cold Land Item 309 - Bituminous Plant Mix (Stocking Maintenance Mix) Item 310 - Bituminous Concrete Surface Course, Hot Land Item 311 - Portland Cement Concrete Pavement

PART IV BRIDGE CONSTRUCTION:

Item 400 - Piling Item 401 - Railing Item 402 - Timber Structures Item 403 - Metal Structures Item 404 - Reinforcing Steel Item 405 - Structural Concrete Item 406 - Pre-Stressed Concrete Structure Item 407 - Concrete Structure Item 408 - Steel Bridges Item 409 - Welded Structural Steel Item 410 - Treated and Untreated Timber Item 411 - Paint

MANPOWER REQUIREMENT AND MINIMUM QUANTITY SURVEY

  1. Formworks

Team: 1 Senior Carpenter

3 Junior Carpenter

  • for every 10 Teams provide 1 Supervisor

MQS: 20.16 sq. m./day/team for Fabrication

8.29 sq. m./day/team for Installation

  1. Steelwork

Team: 1 Lead man

4 Helpers (Benders and Cutters)

MQS: 25 mm. Dia. = 5 to 6 m. length/day

10 mm. Dia. = 10 to 16 m length/day

  1. Tileworks

Team: 1 Senior Mason (Places Tiles)

1 Laborer/Jr. Mason (Mixer/Placer)

MQS: 2 sq.m./day/team

  1. Welding Works (structural steel/penetration)

Team 1 Senior Welder

2 Junior Welder

MQS: 200 kg. Or 0.20 metric tons/day/team

MANPOWER AND EQUIPMENT CAPABILITY/PROJECT PARAMETERS

  • Compaction of Existing Ground After Stripping

Production: 350 cu. m. hr

Equipment: 1 DG Cat Dozer

1 GT Dyna CC-20 Vibro Roller Water Truck (3000 Gals.) 1 3” dia. Water Pump

crew : 1 Operator

2 Drivers 2 Helpers

  • Excavation and Earthmoving

A. Excavation along Earth cuts

Production: 20 cu. m./hr

Equipment: 1 DG Dozer

Crew : 1 Operator

6 – 10 Helper

Manual Labor: 2.50/cu.m./manday (soft)

1.50/cu.m./mandy (rock)

B. Filling with Compaction

Production: 120 cu. m./hr

Equipment: 1 Grader (120 G Cat) 1 GT Dyna CC-20 Vibro Roller 1 Water Truck (3000 gals.) 1 2” dia. Water Pump

Crew : 5 Operators 2 Drivers

C. Hauling/Disposal of Stripped Earth

1) Distance: 320 – 300m

Production: 57 cu. m./hr

Equipment: 1 – 2 ½ cu. yd. 950 Loader

2 – 6 to 8 cu. yd. Dump Trucks

CAPABILITIES OF EQUIPMENT

ITEM TYPE OF WORK CAPABILITY

  1. Dozer
  2. Grader
  3. Pay Loader
  4. Crane Shovel
  5. Sheep foot Roller
  6. No. 3 Road Roller
  7. Tractor-drawn Roller (1-D)
  8. Tander Roller
  9. 5-T Dump truck

10. 2 ½ DT

  1. Buggy
  2. Wheel Borrow
  3. Water Truck
  4. Asphalt Distributor

a) Clearing b) Stripping c) Quarrying d) Excavation e) Pushing

a) sub-grading b) spreading

a) loading

a) loading

a) static rolling (12 passes-15 cm lift) b) vibratory rolling (4 passes-15 cm lift)

a) static rolling (6 passes-15 cm lift)

a) vibratory rolling (6 passes – 2 cm lift)

a) static rolling 96 passes-20 cm lift)

a) Hauling Common Borrow b) Hauling SEBC (Selected borrow, basecourse) c) Hauling Concrete batch class “A”

a) Hauling Common Borrow b) Hauling SEBC (Selected borrow, basecourse c) Hauling concrete batch class “A”

a) Hauling concrete mix

a) Hauling aggregate b) Hauling concrete mix

a) Watering

a) Spraying asphalt prime coat

500 sm/hr 200 sm/hr 50 sm/hr 25 sm/hr 3 cm/hr

300 sm/hr 50 cm/hr

30 cm/hr

35 cm/hr

45 cm/hr 135 cm/hr

24 cm/hr

240 cm/hr

24 cm/hr

3.5 cm /hr 5 cm/trip

3 batch/trip

2.5 cm/trip 2 cm/trip

2 batch/trip

6 cm/trip

2.5 cm/trip 1.7 cm/trip

1000 sm/hr

300 sm/hr

  1. 165 Conc. Mixer
  2. Rock Crusher
  3. Conc. Vibrator
  4. Conc. Floor Finisher
  5. Scraper lowed
  6. Percussion

a) Mixing concrete

a) Crushing mixed sand and gravel

a) Vibrating concrete mix

a) Finishing concrete floor

a) Hauling heap capacity

a) Drilling hard rock b) Drilling loose rock c) Drilling lime stone d) Drilling sticky clay e) Drilling loose clay

9 cm/hr

30 cm/hr

40 cm/hr

140 sm/hr

11 cm/trip

0.75 f/hr 1 f/hr 1.25 f/hr 1.60 f/hr 2.50 f/hr

CAPABILITIES OF MANUAL LABOR

UNIT TYPE OF WORK CAPABILITY

  1. One Man
  2. One Mason & One helper
  3. One Carpenter & One helper
  4. One Mechanic & One helper

a) b) c) d) e) f) g) h) i)

a) b)

a) b)

a)

Excavation loam or sand Excavation clay or heavy soil Excavation of rock Backfilling Spreading, tampering & grading Placing scramble fill Placing binders Clearing undergrowth and small brush Clearing undergrowth and truss

Laying CHB and Adobe Cement finish

Erecting forms Removing forms

Operational maintenance and repair of engineering equipments

0.76 cm/hr 0.61 cm/hr 0.33 cm/hr 1.22 cm/hr 2.09 cm/hr 4.78 cm/hr 9.56 cm/hr 40 sm/hr 20 sm/hr

2 sm/hr 2.80 sm/hr

1.86 sm/hr 1.86 sm/hr

3 equipments

EMPIRICAL REQUIREMENTS FOR VARIOUS STRUCTURES

I. Box Culverts

Forms = 60 bf/cm of concrete Bars = 80 kg/cm of concrete Nails = 1.5 kg/cm of concrete Tie Wire = 0.80 kg/cm of concrete

II. Bridges

Forms = 60 bf/cm of concrete Bars = 120-150 kg/cm of concrete Nails = 2 kg/cm of concrete Tie Wire = 1.1 kg/cm of concrete

III. Grouted Riprap

4 bags cement/cm of riprap 0.68 cm of sand/cm of riprap

EQUIPMENT

DIESEL

FUEL

ENGINE OIL GREASE GEAR OIL GASOLINE

  1. Payloader
  2. Bulldozer
  3. Road Grader
  4. Road Roller (5 tons)
  5. Road Roller (5-8 tons)
  6. Road Roller (10-12 tons)
  7. Crane Truck
  8. Pneumatic Tractor
  9. Truck Tractor with trailer
  10. Water Truck with Pump
  11. Pave
  12. Dump truck
  13. Tractor Crawler (D-7)
  14. Stake Truck 8 tons
  15. Conc. Mixer 4 Bagger
  16. Jeep 4 wheel drive

10 liters/hr

12 liters/hr

10 liters/hr

5 liters/hr

5 liters/hr

2 kms./liter

6 liters/day

3 kms./liter

80 liters/day

1 liter/km

3 liters/day

3 liters/day

3 liters/day

2 liters/day

2 liters/day

2 liters/day

4 liters/day

1 liter/day

1 liter/day

1 .5 liters/day

2 litters/day

1 liter/day

2 liters/day

1 liter/day

½ liter/day

1 liter/day

1 lb./day

1 lb./day

1 lb./day

2 lbs./week

2 lbs./week

liters/week

2 lbs./day

½ lb./day

1 lb./week

1 lb./day

1 lb./day

1 lb./week

2 lbs./day

1 lb./day

½ lb./day

½ lb./day

1 liter/day

1 liter/day

1 liter/day

1 liter/week

1 liter/week

1 liter/day

1 liter/week

1 liter/week brake fluid- 1pint/week

2 liter/week brake fluid- 1 pint/week

1 liter/day

½ liter/day

1 liter/day

6 liters/hr

12 liters/hr

6 liters/hr

8 liters/hr

60 liters/day

30 liters/day

B. 3. BACKHOE

Production (cu. m/hr.) Bank Volume Bucket Canal Structure Creek

C. Quarrying

Production (cu. m/hr.) Bank Volume Dozer ( H. P.) (^) Common Aggregate Col/Bol

Loose Excavated Mat. ( cu .m.)

D. Loading

Production (cu.m/hr.) Bank Volume Bucket (cu. m.) Common Aggregate Cobbles/Boulders

E. Spreading

Production (cu. m/hr.) Cmp. Grader (H.P) Common Aggregate

F. Side Borrow (Common Mat.)

Dozer (H.P)

Production (cu. m/hr.) Compacted Vol.

G. STR. BACKFILL w/Comp.

Dozer (H.P)

Production (cu. m/hr) Compacted Vol.

H. Embankment Compaction

Cap. Cu. m/hr Comp. Volume

Tons Vibratory Static

I. Loading, Spot & Maneuver & Delay Time Used Loader : 1.00 cu. m. Bucket

Dump Truck Capacity Common Materials Road Surface Materials

Cobbles/ Boulders

4.00 cu. m. 6.00 cu. m. 8.00 cu. m.

10 min. 12 min. 17 min.

12 min. 15 min. 17 min.

15 min. 17 min. 20 min.

Wh. Loader .75 – 1.0cm 1.1 - 1.5cm 1.5 – 2.0cm

Compactor Static 5 – 10 tons 11 – 20TC

Vibrator 1 – 3 tons 4 – 6 tons

Water Pump 2” 4” 6” 8”

MIXER

1 Bagger 2 Bagger C. Vibrat. Compressor (cf m)

Water Truck

Cargo Truck 6-7 tons 8-10 tons

Farm Truck

II. MANUAL ASPECT

A. EXCAVATION

A.1. Common Material

TYPE OF WORK

Cap. (cu.m.) Depth of less 2m

Bank Volume excavation more than 2m

Farmditche Canal Structure

A.2 Slight hd. Matl (Ind)

TYPE OF WORK CAP. (cu. m/day/man) Bank Volume

Canal Structure

B. LOADING: Util. five (5) LABORERS

Total time per cubic meter

Sand & gravel 15 min.

Cobles 17 min

Boulder 20 min

C. UNLOADING: Util. 5 LABORER

Total time per cubic meter

Sand & gravel 11 min.

Cobles 12 min

Boulder 15 min

D. CUT, BEND & PLACE RSB

Structure 1 Steel man & 1 Helper with bar cutter

Dam Siphon Bridge Other

96 kgs/day 112 kgs/day 100 kgs/day 80 kgs/day

E. QUARRYING

Capability Cu. m/day/man

Sand & Gravel

Cobles

Boulder

F. DEMOLITION OF CONCRETE

Slab & Wall Massive Conc.

0.35 cu/day/man 0.20 cum/day/man

G. SCREENING OF AGGREGATES

Gravel Sand

4.00 cum/day/man 6.00 cum/day/man

H. MANUAL BACKFILL

Cap : 2.00 cu.m./day/man

I. LAYING OF MATERIALS (cum/day/man) Cobbles= Boulders=1.

J. SPREADING OF AGGREGATE (cum/day/man) Cap : 2.

R. Reinforced Concrete Pipes

DIAMETER

Capability CREW In. cm. Fabrication Installation

1 – Foreman 1 – Mason 1 – Carp./Steel man 12 – Laborers with 1 Bagger Mixer

NOTE:

TIME OF MIXER/DAY=BAGS OF CEMENT /DAY X 10 MIN./BAG

60 MINUTES/HOUR

III. MATERIAL ASPECT

CLASS STRENGTH Max. Aggregate inches

Cement bag/cum

Sand Cum/cum

Gravel Cum/cum

Boulder Cum/cum

A. CONCRETE

a) 3000 psi b) 2400 psi c) 2400 psi

Canal Lining 2400 psi

B. Rubble Masonry w/3000 psi

C. Grouted Riprap

D. Lean Concrete 1000 psi

E. Gravel Blanket

F. Filter Drain

G. Other Materials

- - - C L A S S

TYPE OF STR

Strength Psi

E. lumb. Bdft/cum

1/2pl. wd pcs/cum

Tie wr. Kgs/cum

Nail Kgs/cum

A A A A A C A A

Bridge/Flume Siphon/box culvert Other Struc. MC Other Struc. T.Fac. Rubble Masonry Canal Lining Dam Dam

1.25% RSB

1.20% RSB

1.10% RSB

1.10% RSB

1.00% RSB

1.00% RSB