Effective Scheduling: 6 Processes for Project Time Management, Slides of Project Management

An in-depth exploration of project time management, focusing on the six main processes: activity definition, activity sequencing, activity resource estimating, activity duration estimating, schedule development, and schedule control. Each process is explained with its key outputs and benefits, offering valuable insights for project managers and students.

Typology: Slides

2020/2021

Uploaded on 01/16/2022

tomclacklly0000
tomclacklly0000 🇻🇳

4 documents

1 / 4

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
Project Time Management
In terms of project management, time is the most inflexible of the triple (some say quadruple)
constraints. A schedule may appear easy to formulate, however, estimating the length of time
to perform many tasks is subjective; there is scope, cost, and quality to consider (as well as
the other PMBOK areas). The effects of blow-outs from any of these constraints on the
project schedule cannot easily be anticipated or measured; many projects do not even
attempt to anticipate or measure constraint blow-outs. Also, when people are involved there
are always conflicts of interest, differing opinions, different efficiency levels and work styles,
and cultural differences (and many more), which may impact on the schedule.
With all these possibilities for problems, project time management can still improve
performance. Simply, project time management involves the processes required to ensure
timely completion of the project. This necessarily involves the timely completion of individual
tasks identified in the WBS.
There are six main processes in project time management:
1. Activity definition: identifying the specific activities that the project team members and
stakeholders must perform to produce the project deliverables. An activity (or task or work
package) is an element of work normally found on the Work Breakdown Structure (WBS) that
has an expected duration, cost, and resource requirement. The main outputs include: an
activity list, activity attributes, milestone list.
Therefore, activity definition involves developing a more detailed WBS and supporting
explanations to understand all the work to be done so you can develop realistic duration and
cost estimates.
An activity list is a tabulation of activities to be included in the project schedule that includes:
1. The activity name
2. An activity identifier or number
3. A brief description of the activity
Activity attributes provide more information such as predecessors, successors, logical
relationships, resource requirements, constraints, imposed dates, and assumptions related to
the activity.
A milestone is a significant event that normally has no specified duration, but is designated a
specific delivery date. It often takes several activities and a lot of work to complete a
milestone. They are a useful tool for setting schedule goals and monitoring progress. Project
managers can reduce schedule risk (inherent in the development of complex systems)
through project milestones, a best practice that involves identifying and tracking significant
points or achievements in the project.
There are five key points for using project milestones:
1. Define milestones early in the project and include them in a Gantt chart to provide a
visual guide
pf3
pf4

Partial preview of the text

Download Effective Scheduling: 6 Processes for Project Time Management and more Slides Project Management in PDF only on Docsity!

Project Time Management

In terms of project management, time is the most inflexible of the triple (some say quadruple) constraints. A schedule may appear easy to formulate, however, estimating the length of time to perform many tasks is subjective; there is scope, cost, and quality to consider (as well as the other PMBOK areas). The effects of blow-outs from any of these constraints on the project schedule cannot easily be anticipated or measured; many projects do not even attempt to anticipate or measure constraint blow-outs. Also, when people are involved there are always conflicts of interest, differing opinions, different efficiency levels and work styles, and cultural differences (and many more), which may impact on the schedule. With all these possibilities for problems, project time management can still improve performance. Simply, project time management involves the processes required to ensure timely completion of the project. This necessarily involves the timely completion of individual tasks identified in the WBS. There are six main processes in project time management:

  1. Activity definition: identifying the specific activities that the project team members and stakeholders must perform to produce the project deliverables. An activity (or task or work package) is an element of work normally found on the Work Breakdown Structure (WBS) that has an expected duration, cost, and resource requirement. The main outputs include: an activity list, activity attributes, milestone list. Therefore, activity definition involves developing a more detailed WBS and supporting explanations to understand all the work to be done so you can develop realistic duration and cost estimates. An activity list is a tabulation of activities to be included in the project schedule that includes:
    1. The activity name
    2. An activity identifier or number 3. A brief description of the activity Activity attributes provide more information such as predecessors, successors, logical relationships, resource requirements, constraints, imposed dates, and assumptions related to the activity. A milestone is a significant event that normally has no specified duration, but is designated a specific delivery date. It often takes several activities and a lot of work to complete a milestone. They are a useful tool for setting schedule goals and monitoring progress. Project managers can reduce schedule risk (inherent in the development of complex systems) through project milestones, a best practice that involves identifying and tracking significant points or achievements in the project. There are five key points for using project milestones:
    3. Define milestones early in the project and include them in a Gantt chart to provide a visual guide
  1. Keep milestones small and frequent
  2. The set of milestones must be all-encompassing
  3. Each milestone must be binary, meaning it is either complete or incomplete
  4. Carefully monitor the critical path
  5. Activity sequencing: identifying and documenting the relationships between project activities. The main outputs include: project schedule network diagram, activity list and attribute list updates. This process involves reviewing activities and determining dependencies. A dependency or relationship is the sequencing of project activities or tasks. You must determine dependencies in order to use critical path analysis (refer point 5). Network diagrams are the preferred technique for showing activity sequencing. They are a schematic display of the logical relationships among, or sequencing of, project activities. Two main formats are (refer seminar slides on this topic for examples):
  6. The arrow diagramming method (ADM). Also called the Activity-on-Arrow (AOA) Network Diagram.
  7. The precedence diagramming method (PDM). With the Arrow Diagramming Method (ADM):  Activities are represented by arrows  Nodes or circles are the starting and ending points of activities  Can only show finish-to-start dependencies With the Precedence Diagramming Method:  Activities are represented by boxes  Arrows show relationships between activities  Used by project management software  Better at showing different types of dependencies
  8. Activity resource estimating: estimating how many resources (i.e. people, equipment, and materials) a project team should use to perform project activities. The main outputs include: activity resource requirements, resource breakdown structure, and resource calendar. Before estimating activity duration (the next point), you must have a good idea of the quantity and type of resources that will be assigned to each activity. A resource breakdown structure , which is a hierarchical structure that identifies the project’s resources by category and type, can be helpful with this process.
  9. Activity duration estimating: estimating the number of work periods that are needed to complete individual activities. Duration includes the actual amount of time worked on an activity. Effort is the number of workdays or work hours required to complete a task. The main outputs include: activity duration estimates, activity attribute updates.
  10. Schedule development: involves analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule. The main outputs include:

Tools and techniques include:  Progress reports  A schedule change control system  Project management software, including schedule comparison charts, such as the tracking Gantt chart