Project management focuses on planning and organizing a project and its resources. This includes identifying and managing the lifecycle to be used, applying it to the user-centered design process, formulating the project team, and efficiently guiding the team through all phases until project completion.

Typology: Cheat Sheet

2022/2023

Uploaded on 03/11/2023

joby-jobs
joby-jobs 🇵🇭

4

(1)

4 documents

1 / 3

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
HOTEL CONSTRUCTION SCHEDULE TEMPLATE
One Corporate Building 7/25/2020
CLIENT NAME DATE
4236 Bottom Lane, Findley Lake, New York 14736 10
LOCATION PAGE NO.
Task ID Task Description Start Date End Date
2020
20-Jul
21-Jul
22-Jul
23-Jul
24-Jul
25-Jul
26-Jul
27-Jul
28-Jul
29-Jul
30-Jul
31-Jul
1-Aug
2-Aug
3-Aug
56 Blow-In insulation 7/5/2020 7/6/2020 100%
57 Drywall nailing inspection 7/7/2020 7/7/2020 100%
58 Order finish package 7/7/2020 7/7/2020 100%
59 Tape and texture drywall 7/7/2020 7/14/2020 100%
60 Deliver finish package 7/14/2020 7/14/2020 100%
61 Finish carpentry 7/15/2020 7/20/2020 100% 1
62 Painting 7/20/2020 7/25/2020 100% 1 1 1 1 1 1
63 Phase 4 Exterior Finish
64 Install house wrap 6/21/2020 5/22/2020 100%
65 Roofing 6/22/2020 6/27/2020 100%
66 Masonry 6/22/2020 6/29/2020 100%
67 Siding / Stucco 6/29/2020 7/5/2020 100%
68 Concrete prefinal grade 7/5/2020 6/30/2020 100%
69 Soffit & fascia 7/5/2020 7/7/2020 100%
70 Pour driveway and walk 7/6/2020 7/8/2020 100%
71 Foundation purging 7/8/2020 7/11/2020 100%
72 Exterior painting 7/11/2020 7/12/2020 100%
73 Landscaping 7/12/2020 7/19/2020 100%
74 Phase 5 Interior Finish
75 Order appliances 7/25/2020 7/25/2020 100% 1
76 Tub & shower wall finish 7/25/2020 7/28/2020 0% 1 1 1 1
77 Install resilient/hard floors 7/28/2020 8/2/2020 0% 1 1 1 1 1 1
78 Install cabinets & countertops 8/2/2020 8/3/2020 0% 1 1
79 Deliver appliances 8/2/2020 8/2/2020 0% 1
80 Carpentry pick-up 8/3/2020 8/4/2020 0% 1
81 Install appliances 8/3/2020 8/4/2020 0% 1
%
Completed
pf3

Partial preview of the text

Download building design project management and more Cheat Sheet Project Management in PDF only on Docsity!

HOTEL CONSTRUCTION SCHEDULE TEMPLATE

One Corporate Building 7/25/ CLIENT NAME DATE 4236 Bottom Lane, Findley Lake, New York 14736 10 LOCATION PAGE NO.

Task ID Task Description Start Date End Date

20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 1-Aug 2-Aug 3-Aug 56 Blow-In insulation 7/5/2020 7/6/2020 100% 57 Drywall nailing inspection 7/7/2020 7/7/2020 100% 58 Order finish package 7/7/2020 7/7/2020 100% 59 Tape and texture drywall 7/7/2020 7/14/2020 100% 60 Deliver finish package 7/14/2020 7/14/2020 100% 61 Finish carpentry 7/15/2020 7/20/2020 100% 1 62 Painting 7/20/2020 7/25/2020 100% 1 1 1 1 1 1 63 Phase 4 Exterior Finish 64 Install house wrap 6/21/2020 5/22/2020 100% 65 Roofing 6/22/2020 6/27/2020 100% 66 Masonry 6/22/2020 6/29/2020 100% 67 Siding / Stucco 6/29/2020 7/5/2020 100% 68 Concrete prefinal grade 7/5/2020 6/30/2020 100% 69 Soffit & fascia 7/5/2020 7/7/2020 100% 70 Pour driveway and walk 7/6/2020 7/8/2020 100% 71 Foundation purging 7/8/2020 7/11/2020 100% 72 Exterior painting 7/11/2020 7/12/2020 100% 73 Landscaping 7/12/2020 7/19/2020 100% 74 Phase 5 Interior Finish 75 Order appliances 7/25/2020 7/25/2020 100% 1 76 Tub & shower wall finish 7/25/2020 7/28/2020 0% 1 1 1 1 77 Install resilient/hard floors 7/28/2020 8/2/2020 0% 1 1 1 1 1 1 78 Install cabinets & countertops 8/2/2020 8/3/2020 0% 1 1 79 Deliver appliances 8/2/2020 8/2/2020 0% 1 80 Carpentry pick-up 8/3/2020 8/4/2020 0% 1 81 Install appliances 8/3/2020 8/4/2020 0% 1

Completed

82 Finish electrical 8/3/2020 8/4/2020 0% 1 83 Test appliances 08/05.2020 08/05.2020 0%