



















































Study with the several resources on Docsity
Earn points by helping other students or get them with a premium plan
Prepare for your exams
Study with the several resources on Docsity
Earn points to download
Earn points by helping other students or get them with a premium plan
A comprehensive set of multiple-choice questions and answers related to pjm generation dispatch, covering topics such as system restoration, black start procedures, reserve requirements, and communication protocols. It is a valuable resource for individuals preparing for exams or seeking to enhance their understanding of pjm operations.
Typology: Exams
1 / 59
This page cannot be seen from the preview
Don't miss anything!




















































Which of the following statements is correct concerning PJM assuming frequency control of the restoration process? A) PJM assumes control once an external transmission tie has been established. B) Once an Area Control Error can be calculated, PJM will assume control. C) Whenever it becomes too much of a burden for any one Transmission Owner within the RTO D) Whenever the Transmission Owners within the RTO agree to let PJM control the process. - ✅C) Whenever it becomes too much of a burden for any one Transmission Owner within the RTO During black start restoration, priority access to cranking power should be given to: A) Hot units that can return to service immediately. B) Combustion turbines in areas where the initial disturbance occurred C)Units with black start capability D) Hydro Units - ✅A) Hot units that can return to service immediately. During a restoration, if you are presented with the opportunity to re-connect with the Eastern Interconnection, you should: A)Not pursue this opportunity because you may cause the Eastern Interconnection to become unstable. B) Pursue this opportunity only when you have adequate Dynamic Reserves on your system C) Pursue this opportunity as quickly as possible D) Pursue this opportunity only if you need cranking power for your generating unity - ✅C) Pursue this opportunity as quickly as possible Complete (Total System) Blackouts are characterized by which of the following?
1 - Most common type of blackout 2 - May require coordinating multiple islands 3 - Likely to result in Transmission overloads or other issues 4 - Affects a very large geographical area, and many customers 5 - Most commonly caused by human or switching errors A) 1 & 3 B) 2 & 4 C) 3 & 5 D) 1 - ✅B) 2 & 4 The first step in a system restoration would be to: A) Immediately notify the media of the event B) Restore as much of the area load as possible C) Restore as much under-frequency load as possible D) Verify that communication is functional with your neighbors - ✅D) Verify that communication is functional with your neighbors Why would an offsite power to generating facilities be a priority during the restoration process? A) To provide safe shutdown power for the units B) To meet FERC requirements C) To provide adequate lighting for the plant operators to attempt a restart D) To prepare and expedite the return of the unit - ✅D) To prepare and expedite the return of the unit Factors that help determine the sequence of restoration of off-line generation include (Pick 2): -Generation Type
✅B) 1, 2 and 4 During system restoration, the two categories of reserves are: A) dynamic and secondary B) spinning and quick start C) dynamic and spinning D) spinning and primary - ✅C) dynamic and spinning During a system restoration you have 400MW of Steam capacity, 350MW of CT capacity and 300MW of Hydro capacity restored. Your largest contingency is a 200MW Steam Unit. You have also restored 150MW of under-frequency load. What is your total dynamic reserve? (Load pick-up factors are 5% for steam, 15% for hydro and 25% for CT) A) 142.5MW B) 152.5MW C) 285MW D) 292.5MW - ✅C) 285MW What is the most critical communication path when restoring large load blocks early in a system restoration? A) Between the Generating Unit and the Transmission Owner B) Between PJM and the generating plant C) Between the Generator Owner (or MOC) and the generating unit D) Between the transmission owner and the MOC - ✅A) Between the Generating Unit and the Transmission Owner Your entire system has blacked out due to an event. You receive word from PJM that the entire region is affected as well. Your blackstart generation resources are spread throughout your system, which cover a large area. Which restoration strategy would be the best for you to implement?
A) Combination approach B) Bottom-up Core Island approach C) Top-down approach D) Bottom-up Multiple Island approach - ✅D) Bottom-up multiple island approach During a system restoration, which entity directs the loading of generation, to match the load restored? A) PJM B) The Generating Unit C) The Transmission Owner D) The Generation Owner (or MOC) - ✅C) The Transmission Owner Your entire system has blacked out due to an event. You receive information the your neighboring systems are also blacked out. Your main urban load center restoration strategy would be the best for you to implement? A) Combination approach B) Bottom-up Core Island approach C) Top-down approach D) Bottom-up Multiple Island approach - ✅B) Bottom-up Core Island approach Select the statement that best describes why Minimum Source Requirements have been established: A) To ensure system stability prior to interconnecting with another entity B) To reduce major frequency fluctuations when energizing load C) To prevent or reduce the effects of line changing when energizing EHV transmission D) To ensure that adequate Dynamic Reserves exist prior to interconnection with another entity -
B) 8 hours C) 16 hours D) 24 hours - ✅D) 24 hours During a restoration process, Generation Owners are required to update their progress by submitting a report: A) On an hourly basis B) Every 1/2 hour C) For every unit returning to service D) As conditions on the system change - ✅A) On an hourly basis Concerning PJM requirements for critical start generation, which of the following statements applies to the units capability to maintain frequency? () A) Dynamic offline testing of the units voltage controls B) Picking up an isolated block of loads C) Producing leading and lagging VARs D) Dynamic Off-line testing of the units governor control - ✅B) Picking up an isolated block of loads D) Dynamic Off-line testing of the units governor control During system restoration, a generator should not be loaded above the level of available A) operating reserve B) synchronized reserve C) primary reserve D) dynamic reserve - ✅D) dynamic reserve
C) The Generation Owner D) PJM - ✅B) The Transmission Owner While progressing through your system restoration plan, you come across a transmission line that has both of its breakers closed. The line is far removed from any generation sources. Which of the following statements describes the best course of action you should take? A) The line is clearly faulted and should not be re-energized until all other facilities are in service. B) The line is not faulted and can be re-energized immediately. C) Clear the remaining breakers on the bus and test energize it with a remote line D) Have field personnel check the relay targets at both terminals to determine if the line is faulted - ✅D) Have field personnel check the relay targets at both terminals to determine if the line is faulted Using the following information, determine the maximum amount of load that should be restored (assume a 5% governor droop). Generation Capacity on-line = 1000MW System Load = 800MW System Frequency = 60.5 Hz A) 50MW B) 90MW C) 120MW D) 150MW - ✅A) 50MW Do not restore load blocks that exceed 5% of the synchronized gen capacity Which of the following would be considered as the 'final step' in determining the status of generation after a disturbance or event has occurred?
A) Determine the status of generation that was off-line prior to the event B) Stabilize surviving on-line generation C) Determine what generation survived the event and is still in service D) Determine the status of generation that was off-line prior to the event - ✅C) Determine what generation survived the event and is still in service According to PJM, how many critical Blackstart Unit outages may there be per station? A) 3 B) 2 C) 4 D) 1 - ✅D) 1 2 are allowed per zone but must be at different stations Which of the following are considered as 'critical load' by PJM? A)Two independent feeds into each nuclear facility for station start-up B) Power to pumping plants for underground cables C) Gas infrastructure equipment D) Light and power to critical substations - ✅C) Gas infrastructure equipment During system restoration operations, a member company has a steam capacity of 600MW, combustion turbine capacity of 200MW and 100MW of hydro capacity. The load factors (governor response) are 5%, 25%, and 15% respectively. Also, 50MW of load with underfrequency load shedding enabled has been restored. What is the total governor reserve capability of the company's steam, combustion turbine and hydro units? - ✅95MW
C) Hard copy data (Faxed information, emails) D) Voice circuits or radios - ✅D) Voice circuits or radios According to the NERC EOP-005-2, Requirement 9, each Transmission Owner shall have Black Start testing requirements in place to verify the capability of each generation resource to meet the restoration plan requirements. Under this process, each generator shall be tested at least every A) Year B) Three years C) Five years D) Seven years - ✅B) Three years When connecting islands, how do you know if your system is stable? (Pick 2)
The field windings of a generator are located in which part of the generator?
What is the difference between Dynamic Reserve and Synchronized Reserve? - ✅Dynamic Reserve - (automatic) reserve on generators that is available via governor action and load w/ under frequency relaying Synchronized Reserve - (manual) spinning online gen What are the two types of reserves monitored during a restoration? - ✅Synchronous and Dynamic reserves Which of the following equipment controls generator shaft speed, controls frequency, and adjusts generation for small changes in load? A) Output terminal voltage of the generator B) Governor C) Automatic Voltage Regulator (AVR) D) Exciter - ✅B) Governor A 500MW generator is following economic dispatch and is currently loaded at 400MW. This units ramp rate is 3MW/min. How much Spinning Reserve is available on the unit? A) 10MW Tier 1, 90MW Tier 2 B) 30MW Tier 1, 70MW Tier 2 C) 0MW Tier 1, 100MW Tier 2 D) 30MW Tier 1, 0MW Tier 2 - ✅D) 30MW Tier 1, 0MW Tier 2 What is the deadline for a self-scheduling unit for spinning reserve? A) 1800 on the day before B) 120 minutes before the operation hour
Which of the following statements considering Scarcity Pricing is correct? A) Generation is not subject to the $1000 offer cap during scarcity hours B) The highest market-based offer in the scarcity region set the price for the entire PJM and MISO C) Offer capping remains in effect for units that are not deemed "exempt" D) The highest market-based offer in the scarcity region sets the price for the entire scarcity region - ✅D) The highest market-based offer in the scarcity region sets the price for the entire scarcity region What is the formula to determine a generating units Synchronized Reserve? - ✅- Lesser of: (spin ramp rate * 10 min) or (spin max - current MW level) When is an IRC requested? What types of reserves does it request? - ✅An IRC is typically requested 30-45 min prior to a peak. Types of reserves on the check: -operating reserve -synchronized reserve -quick start (hydro/other) -supplemental Regarding abuses to market rules, what entity holds the authority for enforcement? A) The PJM Market Monitor B) The PJM Members Committee C) NERC D) FERC - ✅FERC Under excited test results means the system is? - ✅Leading (absorbing VARs) What type of units are required to conduct Generator Reactive Testing and how often? -
✅Units: -Any unit 20MW and up -Aggregate units 75MW and up -All black start units -Synchronized condenser units greater than 20MW Frequency: -every 5 years What is the difference between Tier 1 and Tier 2 synchronized reserves? - ✅Tier 1 (economic) - Online units that follow economic dispatch and only partially loaded and therefore are able to increase output within 10 minutes following PJM dispatcher request to event Tier 2 (non-economic) - Resources that offered into the synchronized reserve market and cleared -condensers (CTs and Hydro) transition to online tier 2 condense mode -steam reduced to provide tier 2 support -CTs online at min-operating at a point that deviates from econ -Demand response that can drop load What is Regulation? - ✅Regulation is: