This handout is to explain concepts of Engineering Project Management course with help of examples. It was distributed by Dr. Maaz Khan at Shree Ram Swarup College of Engineering and Management. It includes: Procurement, Management, Plan, Procurement, Framework, Management, Office, Justification, Contract, Decision, Criteria

Typology: Exercises

2011/2012

Uploaded on 07/23/2012

gandhavvv
gandhavvv 🇮🇳

4.5

(45)

75 documents

1 / 2

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
INTRODUCTION
This Procurement Management Plan sets the procurement framework for this project. It
will serve as a guide for managing procurement throughout the life of the project and
will be updated as acquisition needs change. This plan identifies and defines the items to
be procured, the types of contracts to be used in support of this project, the contract
approval process, and decision criteria. The importance of coordinating procurement
activities, establishing firm contract deliverables, and metrics in measuring procurement
activities is included.
PROCUREMENT MANAGEMENT APPROACH
The Project Manager will provide oversight and management for all procurement
activities under this project. The Project Manager will work with the project team to
identify all items to be procured for the successful completion of the project. The Project
Management Office (PMO) will then review the procurement list prior to submitting it to
the contracts and purchasing department. The contracts and purchasing department will
review the procurement items, determine whether it is advantageous to make or buy the
items and the contract.
PROCUREMENT DEFINITION
The following procurement items and/or services have been determined to be essential
for project completion and success. The following list of items/services, justification, and
timeline are pending PMO review for submission to the contracts and purchasing
department:
Item/Service Justification Needed By
Capacitors Needed for manufacturing the hardware; we do not
make this item 20 January 2011
Resistors Needed for manufacturing the hardware; we do not
make this item 20 January 2011
Inductors Needed for manufacturing the hardware; we do not
make this item 27 January 2011
Transformers Needed for manufacturing the hardware; we do not
make this item 27 January 2011
ICs Needed for manufacturing the hardware; we do not
make this item 4 February 2011
docsity.com
pf2

Partial preview of the text

Download Procurement Management Plan Example-Engineering Project Management-Handout and more Exercises Software Project Management in PDF only on Docsity!

I NTRODUCTION

This Procurement Management Plan sets the procurement framework for this project. It will serve as a guide for managing procurement throughout the life of the project and will be updated as acquisition needs change. This plan identifies and defines the items to be procured, the types of contracts to be used in support of this project, the contract approval process, and decision criteria. The importance of coordinating procurement activities, establishing firm contract deliverables, and metrics in measuring procurement activities is included.

PROCUREMENT MANAGEMENT APPROACH

The Project Manager will provide oversight and management for all procurement activities under this project. The Project Manager will work with the project team to identify all items to be procured for the successful completion of the project. The Project Management Office (PMO) will then review the procurement list prior to submitting it to the contracts and purchasing department. The contracts and purchasing department will review the procurement items, determine whether it is advantageous to make or buy the items and the contract.

PROCUREMENT DEFINITION

The following procurement items and/or services have been determined to be essential for project completion and success. The following list of items/services, justification, and timeline are pending PMO review for submission to the contracts and purchasing department:

Item/Service Justification Needed By Capacitors Needed for manufacturing the hardware; we do not make this item

20 January 2011

Resistors Needed for manufacturing the hardware; we do not make this item

20 January 2011

Inductors Needed for manufacturing the hardware; we do not make this item

27 January 2011

Transformers Needed for manufacturing the hardware; we do not make this item

27 January 2011

ICs Needed for manufacturing the hardware; we do not make this item

4 February 2011

docsity.com

In addition to the above list of procurement items, the following individuals are authorized to approve purchases for the project team:

Name Role Dr. Farrukh Kamran Project Manager Aqil Zia Lead Engineer Sheikh Shahrukh Senior Engineer Fahad Sohail Assistant Engineer

TYPE OF C ONTRACT TO BE U SED

All items and services to be procured for this project will be solicited under firm-fixed price contracts. The project team will work with the contracts and purchasing department to define the item types, quantities, services and required delivery dates. The contracts and purchasing department will then solicit bids from various vendors in order to procure the items within the required time frame and at a reasonable cost under the firm fixed price contract once the vendor is selected.

C ONTRACT APPROVAL PROCESS

The first step in the contract approval process is to determine what items or services will require procurement from outside vendors. This will be determined by conducting a cost analysis on products or services which can be provided internally and compared with purchase prices from vendors. Once cost analyses are complete and the list of items and services to be procured externally is finalized, the purchasing and contracts department will send out solicitations to outside vendors. Once solicitations are complete and proposals have been received by all vendors the approval process begins. The first step of this process is to conduct a review of all vendor proposals to determine which meet the criteria established by the project team and the purchasing and contracts department. Purchases less than Rs 1,000 only require the approval of the Project Manager; whereas, purchases greater than Rs 1,000 must be approved by the Contract Review Board. For these larger purchase the contract review board will meet to determine which contract will be accepted. The Contract Review Board consists of representatives from the project team, purchasing and contracts department, finance, and the PMO.

D ECISION CRITERIA

The criteria for the selection and award of procurement contracts under this project will be based on the following decision criteria:

  • Ability of the vendor to provide all items by the required delivery date
  • Quality
  • Cost
  • Expected delivery date
  • Comparison of outsourced cost versus in-sourcing
  • Past performance