This handout is to explain concepts of Engineering Project Management course with help of examples. It was distributed by Dr. Maaz Khan at Shree Ram Swarup College of Engineering and Management. It includes: Work, Breakdown, Structure, Electronic, Ballast, Evaluation, Project, Charter, Preliminary, Scope, Statement

Typology: Exercises

2011/2012

Uploaded on 07/23/2012

gandhavvv
gandhavvv 🇮🇳

4.5

(45)

75 documents

1 / 6

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
INTRODUCTION
The Work Breakdown Structure presented here represents all the work required to
complete this project.
OUTLINE VIEW
1. Electronic Ballast for 200W Induction Lamp
1.1 Initiation
1.1.1 Evaluation & Recommendations
1.1.2 Develop Project Charter
1.1.3 Deliverable: Submit Project Charter
1.1.4 Project Sponsor Reviews Project Charter
1.1.5 Project Charter Signed/Approved
1.2 Planning
1.2.1 Create Preliminary Scope Statement
1.2.2 Determine Project Team
1.2.3 Project Team Kickoff Meeting
1.2.4 Develop Project Plan
1.2.5 Submit Project Plan
1.2.6 Milestone: Project Plan Approval
1.3 Execution
1.3.1 Project Kickoff Meeting
1.3.2 Verify & Validate User Requirements
1.3.3 Design System
1.3.4 Procure Hardware
1.3.5 Install Development System
1.3.6 Testing Phase
1.4 Control
1.4.1 Project Management
1.4.2 Project Status Meetings
1.4.3 Risk Management
1.4.4 Update Project Management Plan
1.5 Closeout
1.5.1 Audit Procurement
1.5.2 Document Lessons Learned
1.5.3 Update Files/Records
1.5.4 Gain Formal Acceptance
1.5.5 Archive Files/Documents
docsity.com
pf3
pf4
pf5

Partial preview of the text

Download WBS Example-Project Management In Engineering-Handout and more Exercises Software Project Management in PDF only on Docsity!

I NTRODUCTION

The Work Breakdown Structure presented here represents all the work required to complete this project.

OUTLINE VIEW

  1. Electronic Ballast for 200W Induction Lamp 1.1 Initiation 1.1.1 Evaluation & Recommendations 1.1.2 Develop Project Charter 1.1.3 Deliverable: Submit Project Charter 1.1.4 Project Sponsor Reviews Project Charter 1.1.5 Project Charter Signed/Approved 1.2 Planning 1.2.1 Create Preliminary Scope Statement 1.2.2 Determine Project Team 1.2.3 Project Team Kickoff Meeting 1.2.4 Develop Project Plan 1.2.5 Submit Project Plan 1.2.6 Milestone: Project Plan Approval 1.3 Execution 1.3.1 Project Kickoff Meeting 1.3.2 Verify & Validate User Requirements 1.3.3 Design System 1.3.4 Procure Hardware 1.3.5 Install Development System 1.3.6 Testing Phase 1.4 Control 1.4.1 Project Management 1.4.2 Project Status Meetings 1.4.3 Risk Management 1.4.4 Update Project Management Plan 1.5 Closeout 1.5.1 Audit Procurement 1.5.2 Document Lessons Learned 1.5.3 Update Files/Records 1.5.4 Gain Formal Acceptance 1.5.5 Archive Files/Documents

HIERARCHICAL STRUCTURE

Level WBS Code Element Name 1 1 Electronic Ballast for 200W Induction Lamp 2 1.1 Initiation 3 1.1.1 Evaluation & Recommendations 3 1.1.2 Develop Project Charter 3 1.1.3 Deliverable: Submit Project Charter 3 1.1.4 Project Sponsor Reviews Project Charter 3 1.1.5 Project Charter Signed/Approved 2 1.2 Planning 3 1.2.1 Create Preliminary Scope Statement 3 1.2.2 Determine Project Team 3 1.2.3 Project Team Kickoff Meeting 3 1.2.4 Develop Project Plan 3 1.2.5 Submit Project Plan 3 1.2.6 Milestone: Project Plan Approval 2 1.3 Execution 3 1.3.1 Project Kickoff Meeting 3 1.3.2 Verify & Validate User Requirements 3 1.3.3 Design System 3 1.3.4 Procure Hardware 3 1.3.5 Install Development System 3 1.3.6 Testing Phase 2 1.4 Control 3 1.4.1 Project Management 3 1.4.2 Project Status Meetings 3 1.4.3 Risk Management 3 1.4.4 Update Project Management Plan 2 1.5 Closeout 3 1.5.1 Audit Procurement 3 1.5.2 Document Lessons Learned 3 1.5.3 Update Files/Records 3 1.5.4 Gain Formal Acceptance 3 1.5.5 Archive Files/Documents

TREE S TRUCTURE V IEW

WBS DICTIONARY

Level WBS Code

Element Name Definition

1 1 Electronic Ballast for 200W Induction Lamp

All work to implement Electronic Ballast for 200W Induction Lamp 2 1.1 Initiation The work to initiate the project. 3 1.1.1 Evaluation & Recommendations Working group to evaluate solution sets and make recommendations. 3 1.1.2 Develop Project Charter Project Manager to develop the Project Charter. 3 1.1.3 Deliverable: Submit Project Charter

Project Charter is delivered to the Project Sponsor. 3 1.1.4 Project Sponsor Reviews Project Charter

Project sponsor reviews the Project Charter. 3 1.1.5 Project Charter Signed/Approved The Project Sponsor signs the Project Charter which authorizes the Project Manager to move to the Planning Process. 2 1. Planning

The work for the planning process for the project. 3 1.2.1 Create Preliminary Scope Statement

Project Manager creates a Preliminary Scope Statement. 3 1.2. Determine Project Team

The Project Manager determines the project team and requests the resources. 3 1.2.

Project Team Kickoff Meeting

The planning process is officially started with a project kickoff meeting which includes the Project Manager, Project Team and Project Sponsor (optional). 3 1.2.

Develop Project Plan

Under the direction of the Project Manager the team develops the project plan. 3 1.2. Submit Project Plan

Project Manager submits the project plan for approval. 3 1.2.

Milestone: Project Plan Approval

The project plan is approved and the Project Manager has permission to proceed to execute the project according to the project plan. 2 1.3 Execution Work involved to execute the project. 3 1.3.

Project Kickoff Meeting

Project Manager conducts a formal kick off meeting with the project team, project stakeholders and project sponsor.